This article explains how to install, configure and commission an Eastron energy meter with a Calculus C04 or C06 gateway.
Objective
A technician must be able to install the Eastron energy meter and CTs, configure the required measurement and Modbus settings, connect the meter to the Calculus gateway and verify that the installation is working correctly.
Scope
This guide covers the installation and configuration of an Eastron energy meter in an electrical distribution board, including:
voltage measurement;
current transformers (CTs);
RS-485 / Modbus communication;
connection to a Calculus C04 or C06 gateway;
Eastron configuration;
commissioning and functional checks.
The measurement chain is:
Voltage measurement and CTs → Eastron energy meter → RS-485 / Modbus → C04/C06 gateway → mobile network → Calculus
The configuration steps in this guide are based on the Eastron SDM630MCT-ML.
Project-specific wiring
Always use the project- and model-specific wiring diagram supplied with the installation for the physical wiring. Eastron SDM630MCT, SDM630MCT-ML and MOD-MID versions can use different connections.
For other Eastron models, follow the supplied wiring diagram and the corresponding model-specific configuration.
Safety first
Warning
Installation and maintenance must only be carried out by authorised and qualified personnel.
Before opening the distribution board or changing any wiring:
De-energise all power supplies.
Secure the installation against accidental re-energisation.
Verify that the installation is de-energised.
Check the exact Eastron model and the corresponding wiring diagram.
Also observe the following safety requirements:
Do not use the Eastron meter as the only electrical fault protection for the installation.
Install the required external protection according to the applicable wiring diagram.
Never open or disconnect the secondary side of an energised CT.
Do not disconnect an RJ12 connection while current is flowing through the primary conductor.
Prepare the installation
Before installation, determine how each outgoing circuit will be measured.
Record at least:
which outgoing circuit is being measured;
which Eastron and channel are assigned to it;
the expected maximum current;
the CT ratio;
the system type;
how phases A, B and C correspond to the voltage measurement;
the Modbus address assigned to each Eastron;
the name of the measured circuit.
Labelling
Use the same identification on the CT, RJ12 cable, Eastron channel and measured circuit. Consistent labelling makes commissioning and troubleshooting considerably easier.
Select the correct system type
The physical voltage connection and the System Type configured on the Eastron must match.
For a standard three-phase installation with neutral, use 3P4W.
System Type | Application |
|---|---|
3P4W | Three phases with neutral |
3P3W | Three phases without neutral |
1P2W | Single phase with neutral |
1P3W | Single-phase three-wire connection according to the model wiring diagram |
Check before power-up
Verify that the configured System Type matches the phases and neutral conductor that are physically connected.
Install the gateway, power supply and antenna
Install the gateway and power supply
Mount the C04/C06 gateway on the DIN rail.
Mount the DIN-rail power supply.
Connect the DC output of the power supply to the gateway according to the polarity indicated on the devices.
Check the output voltage before powering the gateway.
Install the antenna
Install the antenna outside the metal distribution board. The metal enclosure attenuates the mobile signal and can prevent a stable connection.
When installing the antenna:
select a location with sufficient mobile coverage;
keep the antenna and cable away from high-current cables and sources of electrical interference;
use a suitable water- and dust-resistant cable entry if required by the enclosure rating;
avoid sharp bends or compression of the antenna cable;
connect the antenna before commissioning the gateway.
Connect the Eastron electrically
Connect the Eastron power supply and voltage measurement according to the wiring diagram for the supplied model.
Check the model designation before using any terminal numbers.
Use the supplied wiring diagram
SDM630MCT, SDM630MCT-ML and MOD-MID versions can have different terminal assignments. Do not copy terminal numbers from another Eastron model or from a previous installation.
After wiring, verify that:
L1, L2, L3 and N are connected according to the model-specific diagram;
the required external protection has been installed;
the DIN-rail power supply and Eastron are supplied correctly;
all connections are securely fastened and clearly labelled.
Install the CTs
Correct phase matching and CT direction are required for reliable current and power measurements.
Fully de-energise the installation and verify that it is de-energised.
Install one CT around each phase to be measured or route the phase conductors through the corresponding CT openings.
Keep the neutral conductor outside the CT.
Position P1 towards the supply side and P2 towards the load side.
Connect the RJ12 cable to the correct CT input on the Eastron.
Push the RJ12 connector fully into place.
Verify that voltage phase A corresponds to CT phase A, B to B and C to C.
Label the CT, RJ12 cable and Eastron channel with the same identification.
Negative active power
A negative active power value often indicates a reversed CT or incorrect phase matching.
Check the physical wiring first. Only use the
REVsetting after the wiring and phase matching have been verified.
Connect RS-485 / Modbus
Connect the Eastron to the gateway using RS-485.
For the C06 setup described in this guide, use the following connections:
Wire colour | Eastron | Gateway |
|---|---|---|
Brown | A | A+ |
Yellow | B | B- |
Green | GND | GND |
For a C04 installation, follow the project-specific wiring diagram for the gateway connection.
All devices connected to the same RS-485 bus must use the same communication parameters. Each physical Eastron must have a unique Modbus address.
Use the following settings:
Setting | Value |
|---|---|
SET Addr QNTY | 1 |
Baud rate | 9600 |
Data bits | 8 |
Parity | NONE |
Stop bits | 1 |
Serial format | 9600 / 8N1 |
C06 termination
For the C06 setup described in this guide, set the RS485 Terminator to
OFF.
Standard measurement output order
Calculus normally uses four measurement outputs per Eastron.
Use the following order when connecting and labelling the measured circuits:
Calculus output | Eastron | Channel |
|---|---|---|
Output 01 | Eastron 1 | Channel 1 |
Output 02 | Eastron 1 | Channel 2 |
Output 03 | Eastron 1 | Channel 3 |
Output 04 | Eastron 1 | Channel 4 |
Output 05 | Eastron 2 | Channel 1 |
Output 06 | Eastron 2 | Channel 2 |
Output 07 | Eastron 2 | Channel 3 |
Output 08 | Eastron 2 | Channel 4 |
Output 09 | Eastron 3 | Channel 1 |
Output 10 | Eastron 3 | Channel 2 |
Output 11 | Eastron 3 | Channel 3 |
Output 12 | Eastron 3 | Channel 4 |
Output 13 | Eastron 4 | Channel 1 |
Output 14 | Eastron 4 | Channel 2 |
Output 15 | Eastron 4 | Channel 3 |
Output 16 | Eastron 4 | Channel 4 |
Project configuration
The project-specific configuration always takes priority. If the assigned mapping differs from this standard order, use the mapping defined for that project.
Configure the Eastron
Configure each Eastron before performing the final functional test.
Configure and test one meter at a time. This makes it easier to verify addresses and channels and prevents multiple devices from obscuring an addressing problem.
Controls
Use the following buttons to navigate through the Eastron settings:
Control | Function |
|---|---|
| Increase value / previous option |
| Decrease value / next option |
Short press | Move to the next position |
Hold | Open settings or confirm |
Open the settings menu
Hold
Efor approximately three seconds.When
PASSappears, enter the password usingM,PandE.Use the default password
1000.Hold
Eto confirm.
Configure address mode and slave ID
Required setting
Set
SET Addr QNTYto1.The complete physical Eastron then uses one Modbus address, and channels CH01 to CH04 share the same slave ID.
Do not use QNTY 2, 3 or 4 for this Calculus setup.
If CH01 or CH02 appears while configuring the address, the meter is still operating in multi-address mode.
Use the following standard slave IDs:
Eastron | QNTY | Slave ID |
|---|---|---|
Eastron 1 | 1 | 001 |
Eastron 2 | 1 | 002 |
Eastron 3 | 1 | 003 |
Eastron 4 | 1 | 004 |
To configure the address:
Open
SET Addrand thenSET Addr QNTY.Set
SET Addr QNTYto1.Hold
Eto confirm.Open
SET Addragain.Set the assigned slave ID for the complete meter.
Hold
Eto confirm.
Configure the communication settings
Set the following communication parameters:
Parameter | Value | Display |
|---|---|---|
Baud rate | 9600 |
|
Parity | NONE |
|
Stop bits | 1 |
|
Data bits | 8 | Fixed Modbus RTU setting |
Configure CT1
CT1 defines the rated primary current of the connected CT.
The configured value must match the rating shown on the CT. An incorrect CT1 setting causes proportionally incorrect measurement values.
Examples:
Connected CT | CT1 |
|---|---|
60 A / 100 mA | 60 A |
125 A / 100 mA | 125 A |
400 A / 100 mA | 400 A |
To configure CT1:
Open
SET CT1.Select the required channel from
CH01toCH04.Select
L1,L2andL3in sequence.Set the primary CT value for each phase.
Hold
Eto confirm.Repeat these steps for every channel that is used.
Check CT2
CT2 is read-only.
For a 100 mA CT version, the displayed value should be:
0.1 A
Configure System Type
Open SET SYS and select the system type that matches the physical voltage connection.
For a three-phase installation with neutral, use:
3P4W
Check CT direction
The normal CT direction is:
FRD (forward)
with:
P1 on the supply side;
P2 on the load side.
Use REV only if a physical check confirms that the CT has been installed in reverse and correcting the physical installation is not practical.
Start the installation
Start the installation in stages. This makes it easier to identify which meter causes an addressing or communication problem.
After changing addresses or communication settings, fully power down the gateway and all Eastron meters.
Power the installation back on.
Test Eastron 1 first.
Add the remaining Eastron meters one at a time.
After adding each meter, verify that all previously connected meters and channels remain reachable.
Commission the installation
Complete the following checks before handing over the installation.
Electrical installation
All terminals are secure and connected according to the correct wiring diagram.
CTs, RJ12 cables and Eastron channels are clearly labelled.
The antenna is installed outside the distribution board and connected.
The gateway and all Eastron meters power up correctly.
Eastron configuration
The correct System Type is configured.
The correct CT1 values are configured.
SET Addr QNTYis set to1.Every Eastron has a unique slave ID.
Baud rate is set to
9600.Parity is set to
NONE.Stop bits are set to
1.
Functional check
Voltages L1, L2 and L3 are present and plausible.
Every measurement circuit shows a plausible current and active power value.
There are no unexpected negative active power values.
Modbus communication between the Eastron meters and gateway is working.
The gateway comes online through the installed SIM card.
Every measurement circuit in use has been functionally tested with a load.
Troubleshooting
Problem | Possible cause | Check / action |
|---|---|---|
Gateway does not start | Missing or incorrect DC supply | Check the power supply, output voltage, polarity and wiring. |
Gateway remains offline | Antenna, mobile reception or power supply | Check the antenna connection and position, power supply and gateway status LEDs. |
No Eastron data | Modbus wiring or configuration | Check A/B/GND, slave ID, baud rate, parity, stop bits and QNTY. |
Meters work separately but not together | Duplicate slave ID or incorrect QNTY | Check that QNTY = 1 and that each Eastron has a unique slave ID. |
CH01 or CH02 appears when setting the address | Multi-address mode is active | Set |
One channel is missing | RJ12 connection or incorrect channel | Check the RJ12 connection and the Eastron channel being used. |
Zero values | No load, incorrect CT installation or incorrect phase matching | Check the connected load, CT installation, phase matching and CT1 value. |
Negative active power | CT direction or phase matching | Check P1/P2 and phase matching before using |
Implausible measurement value | Incorrect CT ratio or System Type | Check CT1 and |
Record the installation
Record the installed measurement configuration during handover. This information makes future checks and troubleshooting considerably easier.
Record at least:
gateway type and serial number;
Eastron type and serial number(s);
SET Addr QNTYand slave ID for each Eastron;baud rate, parity and stop bits;
CT type and current ratio for each measurement output in use;
CT1 value for each channel and phase in use;
name of each measured circuit;
configured System Type;
any CT directions changed to
REVin software.
Quick reference for the technician
Item | Setting / connection |
|---|---|
Communication | RS-485 / Modbus RTU |
SET Addr QNTY | 1 |
Eastron 1 | Slave ID 001 |
Eastron 2 | Slave ID 002 |
Eastron 3 | Slave ID 003 |
Eastron 4 | Slave ID 004 |
Baud rate | 9600 |
Data bits | 8 |
Parity | NONE |
Stop bits | 1 |
Serial format | 9600 / 8N1 |
CT direction | FRD |
CT2 for 100 mA version | 0.1 A |
Standard three-phase system with neutral | 3P4W |
C06 RS485 Terminator | OFF |
Final check
Physical wiring checked against the project-specific diagram
CT direction and phase matching checked
CT1 values checked
QNTY = 1
Unique slave ID assigned to every Eastron
RS-485 communication settings checked
All required channels return plausible measurements
Gateway online
Modbus communication stable
Installation details recorded for handover
Ready for handover
The installation is ready for handover when the wiring has been checked, all Eastron meters have unique addresses, the measurement values are plausible and Modbus communication is stable.